BASE METALS

Crusher issue causes loss for Copper Mountain

Copper Mountain Mining saw a weak start to the year with results below consensus expectations for the quarter to March 31.

Copper Mountain Mining's Copper Mountain mine in British Columbia, Canada

Copper Mountain Mining's Copper Mountain mine in British Columbia, Canada

Copper Mountain reported a net loss of C$4.2 million on sales of $93.9 million. The company ended the quarter with cash and equivalents of $159.2 million. It also increased its all-in cost guidance for the year from to US$2.25 to US$2.75 per pound.

The company produced 13.2 million pounds of copper, 5,135 ounces of gold and 55,993oz of silver in the quarter for 15.6 million pounds of copper equivalent, 48% lower than the record production achieved in the prior year.

The company said this was primarily driven by lower mill head grade and lower throughput resulting from damage to the secondary crusher at its Copper Mountain mine in British Columbia, Canada. A new main shaft was installed in the damaged crusher in April and the mill is ramping up to full capacity.

"Lower production was a result of operating at reduced mill throughput and lower grade, as we continued to run the secondary crusher at lower power draw due to the damaged main shaft, resulting in low and very coarse feed to the mill.  This issue is now resolved," said Copper Mountain Mining president and CEO Gil Clausen.

The crusher issue contributed to C1 cash costs rising to US$3.58/lb in the quarter compared with US$1.15 in the prior year period, primarily due to lower production, temporary contractor maintenance expenses, temporary contract crushing expenditures and inflationary pressures on costs, particularly diesel. The all-in cost was US$5.08/lb.

"Given the previously announced damage, in our view, a slower production start to the year was expected, though the production results were lower than expected with costs well above expectations," said BMO Capital Markets analyst Rene Cartier.

The company is ramping-up the milling circuit to full capacity of 45,000 tonnes per day and it expects to be at this level through the balance of 2022. It also said higher grade ore from phase 4 of the main pit is planned for the second semester with the newly developed North pit providing the bulk of the feed through the June quarter. It reiterated its 80-90Mlb of copper production guidance for the year.

Copper Mountain also commissioned the trolley assist project to reduce carbon emissions at its Copper Mountain mine by at least 30%.

The company also entered into zero-cost collar options for 3.3Mlb of copper per month through 2022 with a floor price of US$4/lb and an average ceiling price of US$4.91/lb.

Shares in Copper Mountain Mining lost almost 9% in early trading to $2.90, valuing the company at $610 million.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.