Bunker Hill PFS paves way for construction decision

Bunker Hill has released a prefeasibility study for the first phase of the restart of the Bunk Hill base metal and silver mine in Idaho, USA, which views an after-tax NPV8% of US$52 million and IRR of 36%.

The initial discovery phase began at Bunker Hill in 1885

The initial discovery phase began at Bunker Hill in 1885

Bunker Hill CEO Sam Ash said the company intends to commence "profitable, sustainable, modern operations" by the end of 2023.

"As demonstrated in our PFS, Bunker Hill is a sustainable low-risk, high-margin asset with the potential to generate free cash flow of over $25 million per year while contributing to strategic metal production in the United States beginning in 2024," Ash said.

"We are now focused on driving forward to a formal construction decision while maintaining momentum with ongoing restart activities," he said.

An initial capital expenditure of $55 million is to achieve an expanded 1,800 tonnes per day operation, leveraging mineral endowment of "the largest-scale and shallowest major mine" in Idaho's Silver Valley, and "one of the most prolific mines in US history," the company said.

The mine has been in care and maintenance since 1991.

The PFS views a 2.1 year payback period while the company is presented with a "rapid restart" of 16 months to commercial production, it said.

The phase 1 mine plan is for zinc equivalent production of 475 million pounds at a zinc equivalent grade of 8.5%, including 317 million pounds of zinc, 146 million pounds of lead, and 3 million ounces of silver.

The all-in sustaining cost is expected at $0.77 per payable pound of zinc, net of by-products.

The mine is intended to be a first step for Bunker Hill in its plan in consolidating a portfolio of North American precious-metal assets with a focus on silver.

From initial discovery in 1885, until the mine's closure, production totaled 42.77 million tons at an average grade of 8.43% lead, 3.52 ounces silver per ton and 4.52% zinc, the company said.

Bunker Hill had a share price of C$0.093 (US$0.07) on 6 September, with a market capitalisation of C$20.42 million.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.

editions

Mining Journal Intelligence Global Leadership Report 2023: Social licence

Gain insights into social licence trends and best practices from interviews with 20+ top mining company executives and an industrywide survey.