Ascot gives Premier update

Ascot Resources has provided an update on the construction of its Premier gold mine in British Columbia, excluding mine development. It is now 48% complete, with engineering at 99% and procurement at 99%. It said the project is on schedule and budget for first gold production in the March quarter of 2024.

 The tailings south dam earthworks at Ascot Resources' Premier in British Columbia, Canada

The tailings south dam earthworks at Ascot Resources' Premier in British Columbia, Canada

Construction of the processing plant and associated surface infrastructure is expected to be completed and pre-commissioned by the year's end. Completion of the tailings dam improvements and start-up of...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

A growing series of reports, each focused on a key discussion point for the farming sector, brought to you by the Kondinin team.

editions

Mining Journal Intelligence Project Pipeline Handbook 2024

View our 50 top mining projects, handpicked using a unique, objective selection process from a database of 450+ global assets.

editions

Mining Journal Intelligence Investor Sentiment Report 2024

Survey revealing the plans, priorities, and preferences of 120+ mining investors and their expectations for the sector in 2024.

editions

Mining Journal Intelligence Mining Equities Report 2023

Access an exclusive, inside look on the quarterly mining IPOs and secondary raisings data and mining equities performance tables with an annual Stock Exchange Comparisons supplement.

editions

Mining Journal Intelligence World Risk Report 2023 (feat. MineHutte ratings)

A detailed analysis of mining investment risks across 121 jurisdictions globally, built on 11 ‘hard risk’ metrics and an industrywide survey.